Approved an increase in the Supplemental Work Allowance for the Demolition and Temporary Provisions of Main Jail South.

Department: Facilities and Fleet Department
Sponsors:  
Category: Construction Contracts

On December 12, 2018, Item 17, the Board of Supervisors (Board) awarded a contract in the amount of $10,111,258, with a SWA of $2,000,000 for a total encumbrance of $12,111,258 to Rodan Builders, Inc., with a construction time of 195 calendar days.