Department: Facilities and Fleet Department
Sponsors:
Category: Construction Contracts
An increase in the SWA is required to authorize additional spending on the contract and will allow for the procurement and installation of generator wiring, a final generator power connection, and additional asbestos abatement. The current SWA of $4,000,000 has been committed for the change from temporary to permanent generators and unforeseen conditions to date.